Construction of Sentinel Marine's new buildings are progressing well in Fujian South East Shipyard, China. Steel cutting had commenced and we are expecting the first launch for ABLE SENTINEL in March 2012, with delivery in May 2012.
Her sister, the BRAVE SENTINEL, will launch in June 2012, with delivery in August 2012.
The third vessel, CONSTANT SENTINEL, is expected to deliver in November 2012.